A plumber finishes rough-in a day early. What is the lead carpenter's best immediate action?
-
A
Notify the inspector and schedule the next trade early
-
B
Wait until the original schedule date to call the next trade
-
C
Begin closing in walls without inspection
-
D
Send the plumber home and adjust the project end date