CLC Client Relations & Change Orders 2 — Questions and Answers
Question 1: A homeowner verbally approves additional work during a job site visit but later denies agreeing to it. What should the lead carpenter have done?
- Proceeded based on the verbal approval since a witness was present
- Obtained a written change order signed by the homeowner before starting the work (Correct answer)
- Called the office to report the verbal agreement and continued working
- Sent a follow-up email after completing the work to document the approval
Correct answer: Obtained a written change order signed by the homeowner before starting the work
A signed written change order is required before starting any additional work to protect both parties and ensure clear agreement on scope and cost.
Question 2: When presenting a change order to a client, what should always be included in addition to the price?
- The contractor's profit margin on the change
- A description of work scope, materials, and impact on the project schedule (Correct answer)
- The names of the crew members who will perform the work
- A comparison to what competitors would charge for the same work
Correct answer: A description of work scope, materials, and impact on the project schedule
A complete change order includes scope of work, materials, cost, and any schedule impact so the client can make a fully informed decision.
Question 3: A client asks you to skip a change order for a small $150 addition because 'it's not worth the paperwork.' What is the best response?
- Agree, since small amounts rarely cause disputes
- Complete the work and add it to the final invoice
- Explain that all scope changes require documentation regardless of size (Correct answer)
- Ask your supervisor to make the call
Correct answer: Explain that all scope changes require documentation regardless of size
All scope changes, regardless of dollar amount, should be documented to prevent misunderstandings and protect the contractor's interests.
Question 4: Which communication method is most effective when a client becomes upset about unexpected costs?
- Send a detailed written explanation and avoid further discussion until they calm down
- Listen actively, acknowledge their concern, then explain how the cost arose using the change order (Correct answer)
- Remind them that the contract requires payment for all approved changes
- Offer a discount to resolve the dispute quickly
Correct answer: Listen actively, acknowledge their concern, then explain how the cost arose using the change order
Active listening and acknowledgment de-escalate tension before presenting the factual explanation referenced in signed documentation.
Question 5: A client requests a change that would conflict with local building code. What should the lead carpenter do?
- Complete the change since the client bears liability for their own home
- Inform the client the change cannot be made as requested due to code requirements (Correct answer)
- Complete the work and note the code conflict in the change order
- Refer the decision entirely to the building inspector
Correct answer: Inform the client the change cannot be made as requested due to code requirements
A lead carpenter must refuse any change that violates building codes and clearly explain why the requested modification cannot be performed.
Question 6: What is the primary purpose of a change order log maintained by the lead carpenter?
- To track subcontractor billing for additional work
- To provide a running record of all approved scope changes, costs, and signatures (Correct answer)
- To document client complaints for dispute resolution
- To calculate bonuses for crew members who complete extra work
Correct answer: To provide a running record of all approved scope changes, costs, and signatures
A change order log gives the lead carpenter an organized record of every modification to verify approvals and reconcile the final invoice.
Question 7: A change order increases the project completion date by one week. Who is responsible for communicating this schedule impact to the client?
- The project estimator who priced the change
- The lead carpenter managing the job site (Correct answer)
- The subcontractor performing the additional work
- The office administrator processing the change order paperwork
Correct answer: The lead carpenter managing the job site
The lead carpenter is the primary client contact on site and is responsible for communicating all schedule impacts arising from approved changes.
A homeowner verbally approves additional work during a job site visit but later denies agreeing to it.
What should the lead carpenter have done?