Lighting System Commissioning & Quality Assurance Flashcards

7 cards from real CLC practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Lighting System Commissioning & Quality Assurance flashcards as text
  1. What is the primary purpose of lighting commissioning?

    Answer: To verify that a lighting system is installed and operates according to design intent

    Lighting commissioning verifies that the installed system performs as specified in the design documents and meets the owner's requirements.

  2. Which document establishes the intended performance expectations of a lighting system before commissioning begins?

    Answer: Owner's Project Requirements (OPR)

    The Owner's Project Requirements (OPR) documents the functional requirements and expectations the lighting system must meet throughout the project.

  3. Which measurement instrument is most appropriate for verifying horizontal illuminance levels during commissioning?

    Answer: Illuminance meter (footcandle meter)

    An illuminance meter measures footcandles or lux at a surface, which is the standard method for verifying horizontal illuminance against design targets.

  4. What is a 'punch list' in the context of a lighting commissioning project?

    Answer: A list of deficiencies, incomplete items, or corrections needed before project closeout

    A punch list documents items that must be corrected or completed before the project can be officially closed out and accepted by the owner.

  5. During commissioning of occupancy sensors, which parameter is most critical to verify for energy performance?

    Answer: The time delay before lights turn off after the space becomes unoccupied

    The time-delay (timeout) setting determines when lights extinguish after the last detected motion, directly affecting energy savings and occupant satisfaction.

  6. What does 'as-built documentation' provide at the completion of a lighting project?

    Answer: An accurate record of how the lighting system was actually installed, including all field modifications

    As-built drawings record the final installed conditions, capturing all deviations from the original design that occurred during construction.

  7. At what stage of a project should commissioning activities ideally begin?

    Answer: During schematic design, when project goals and requirements are being established

    Beginning commissioning during the design phase allows performance requirements to be incorporated into specifications and reduces costly changes during construction.