During construction administration, a Contractor submits a Request for Information (RFI). The landscape architect's primary obligation is to:
-
A
Immediately issue a change order
-
B
Respond with clarification within a reasonable time without changing the contract scope
-
C
Direct the contractor to proceed without clarification
-
D
Refer all RFIs to the civil engineer