  1. A UK embassy buys supplies in Japanese yen. The total is ¥892,500. If the exchange rate is £1 = ¥185, what is the sterling cost?

    Answer: £4,825

    Sterling cost = ¥892,500 / 185 = £4,824.32, approximately £4,825.

  2. A government fleet of vehicles uses 12,800 litres of diesel per month. Diesel costs 142.9p per litre. What is the monthly fuel cost to the nearest pound?

    Answer: £18,291

    Cost = 12,800 x £1.429 = £18,291.20. Converting 142.9p to pounds gives £1.429, then multiply by the volume in litres.

  3. A civil servant flies from London to Washington DC (5,900 km) and claims a flat rate of £125 per 1,000 km. How much is the flight allowance?

    Answer: £737.50

    Number of 1,000 km units = 5,900 / 1,000 = 5.9. Allowance = 5.9 x £125 = £737.50.

  4. An office thermostat is set to 21 degrees Celsius. Using the formula F = (C x 9/5) + 32, what is this temperature in Fahrenheit?

    Answer: 69.8°F

    F = (21 x 9/5) + 32 = (21 x 1.8) + 32 = 37.8 + 32 = 69.8°F.

  5. A government project has a budget of £2.4 million allocated over 18 months. If 7 months have passed and £980,000 has been spent, is the project on budget based on a linear spend profile?

    Answer: Overspent by £46,667

    Monthly budget = £2,400,000 / 18 = £133,333.33. Expected spend after 7 months = 7 x £133,333.33 = £933,333. Actual spend = £980,000. The project is overspent by £980,000 minus £933,333 = £46,667.

  6. A department is comparing two suppliers. Supplier A charges €18,500 (exchange rate £1 = €1.16) and Supplier B charges £15,200. Which supplier is cheaper and by how much?

    Answer: Supplier B is cheaper by £748

    Supplier A in sterling = €18,500 / 1.16 = £15,948.28. Supplier B = £15,200. Supplier B is cheaper by £15,948 minus £15,200 = £748.