Civil Service Numerical Reasoning Test Time, Speed and Logical Numerical Reasoning 4
Free · Instant Results
A project deadline is in 6 weeks. Work must be completed in the first 4 weeks to allow 2 weeks for review. If there are 5 working days per week, how many working days are available for the work itself?