Which scheduling technique is most appropriate when activity durations are uncertain and probabilistic estimates are needed?
-
A
CPM (Critical Path Method)
-
B
PERT (Program Evaluation and Review Technique)
-
C
Gantt chart scheduling
-
D
Linear scheduling method