Civil Engineering PE Practice Test

Civil Engineering PE Project Planning and Estimating 2

Free · Instant Results

A project has the following activities with durations: A=5d, B=3d, C=4d, D=6d, E=2d. The network shows A→C→E and A→B→D→E as paths. What is the critical path duration?
▶ Start Practice Test