A contractor submits a method statement that does not adequately address a specific risk on site. The principal contractor should:
-
A
Allow the work to proceed and monitor it closely
-
B
Refuse to allow the work to start and require the method statement to be revised and resubmitted before the activity commences
-
C
Accept it if the contractor has a good track record
-
D
Add their own risk controls without informing the contractor