Under CDM 2015, what must appear on the F10 notification submitted to the HSE?
-
A
The contact details of all workers on site
-
B
Project details including client, principal designer and principal contractor contact details, site address, and expected start and end dates
-
C
The Construction Phase Plan in full
-
D
A list of all planned risk assessments