A secured creditor holds a lien on equipment worth $500,000 but is owed $800,000. Under Section 506, what is the creditor's status regarding the $300,000 deficiency?
-
A
Fully secured claim for the entire $800,000
-
B
Two claims: $500,000 secured and $300,000 general unsecured
-
C
Administrative expense priority for the deficiency
-
D
The deficiency is discharged upon plan confirmation