← All CIMA Flashcard Decks

Management Accounting Flashcards

7 cards from real CIMA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Management Accounting flashcards as text
  1. A company has a margin of safety of 25%. This means:

    Answer: Actual sales can fall 25% before the company makes a loss

    A margin of safety of 25% indicates actual sales exceed breakeven by 25%, so sales could drop by that amount before a loss occurs.

  2. Process costing is most appropriate for which type of production?

    Answer: Oil refining producing homogeneous outputs

    Process costing suits continuous, mass production of identical or near-identical units such as oil refining, chemicals, or food processing.

  3. Normal loss in a process account is valued at:

    Answer: Net realizable value (scrap value)

    Normal loss is valued at its scrap/net realizable value; its cost is absorbed into the remaining good output.

  4. Which of the following best describes a 'relevant cost' in decision-making?

    Answer: A future incremental cash cost that differs between alternatives

    Relevant costs are future, incremental cash flows that differ between the decision alternatives being evaluated.

  5. A company is considering dropping a product line. Which of the following would NOT be relevant to the decision?

    Answer: Historical development costs already spent

    Historical development costs are sunk costs — they have already been incurred and cannot be recovered, making them irrelevant to the decision.

  6. If a company operates at full capacity and receives a special order, the minimum price it should charge per unit is:

    Answer: Variable cost plus opportunity cost per unit

    At full capacity, accepting a special order means sacrificing existing contribution (opportunity cost), so the minimum price must cover variable cost plus that lost contribution.

  7. The internal rate of return (IRR) of a project is best described as:

    Answer: The discount rate at which the NPV of the project equals zero

    The IRR is the discount rate that makes the NPV of all cash flows from a project equal to zero.