Management Accounting Flashcards
7 cards from real CIMA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Management Accounting flashcards as text
A company has a margin of safety of 25%. This means:
Answer: Actual sales can fall 25% before the company makes a loss
A margin of safety of 25% indicates actual sales exceed breakeven by 25%, so sales could drop by that amount before a loss occurs.
Process costing is most appropriate for which type of production?
Answer: Oil refining producing homogeneous outputs
Process costing suits continuous, mass production of identical or near-identical units such as oil refining, chemicals, or food processing.
Normal loss in a process account is valued at:
Answer: Net realizable value (scrap value)
Normal loss is valued at its scrap/net realizable value; its cost is absorbed into the remaining good output.
Which of the following best describes a 'relevant cost' in decision-making?
Answer: A future incremental cash cost that differs between alternatives
Relevant costs are future, incremental cash flows that differ between the decision alternatives being evaluated.
A company is considering dropping a product line. Which of the following would NOT be relevant to the decision?
Answer: Historical development costs already spent
Historical development costs are sunk costs — they have already been incurred and cannot be recovered, making them irrelevant to the decision.
If a company operates at full capacity and receives a special order, the minimum price it should charge per unit is:
Answer: Variable cost plus opportunity cost per unit
At full capacity, accepting a special order means sacrificing existing contribution (opportunity cost), so the minimum price must cover variable cost plus that lost contribution.
The internal rate of return (IRR) of a project is best described as:
Answer: The discount rate at which the NPV of the project equals zero
The IRR is the discount rate that makes the NPV of all cash flows from a project equal to zero.