Under the net present value method, a project should be accepted when:
Answer: NPV is greater than zero
A positive NPV means the project earns more than the required rate of return and adds value.
The internal rate of return is the discount rate at which:
Answer: Net present value equals zero
IRR is the rate that makes the present value of inflows equal the initial investment.
Which is a key weakness of the simple payback method?
Answer: It ignores the time value of money and cash flows after payback
Simple payback ignores discounting and any cash flows received after the investment is recovered.
A project costs $60,000 and generates even annual cash inflows of $15,000. What is its payback period?
Answer: 4 years
Payback = $60,000 / $15,000 = 4 years.
When NPV and IRR rank two mutually exclusive projects differently, which method should generally be followed?
Answer: NPV, because it measures absolute value added
NPV directly measures wealth created and assumes reinvestment at the cost of capital, so it is preferred.
In a capital budgeting analysis, how should a sunk cost incurred last year be treated?
Answer: Ignored, because it is not affected by the decision
Sunk costs have already been incurred and cannot change, so they are irrelevant to the decision.
The profitability index is calculated as:
Answer: Present value of future cash flows divided by initial investment
A profitability index above 1.0 indicates a positive NPV and is useful when capital is rationed.