Under EPA's Risk Management Program (RMP) rule (40 CFR Part 68), a Program 3 process requires which of the following elements NOT required for Program 2?
Answer: Process Hazard Analysis using a specific OSHA PSM methodology
Program 3 requires a full PHA using OSHA PSM-listed methodologies (HAZOP, fault tree, etc.), whereas Program 2 allows simpler hazard reviews.
A facility's waste characterization shows a liquid waste with pH 2.1. Under 40 CFR 261.22, this waste is classified as hazardous due to which characteristic?
Answer: Corrosivity
A liquid with pH ≤ 2 or ≥ 12.5 exhibits the RCRA corrosivity characteristic.
When labeling an acute hazardous waste container at a large quantity generator facility, what is the maximum allowable accumulation time before the container must be moved to an approved storage area?
Answer: 1 day
Acute hazardous wastes (P-listed) must be moved from satellite accumulation areas to the central storage area within 1 day of reaching the container limit.
A facility manager is reviewing a chemical's SDS and notes a vapor density of 1.8 (air = 1.0). This physical property indicates that the vapor will most likely do what in the facility?
Answer: Sink and accumulate in low-lying areas and confined spaces
Vapors with density greater than 1.0 are heavier than air and will settle in pits, trenches, and floor-level confined spaces.
Under OSHA 29 CFR 1910.147 (Lockout/Tagout), before performing maintenance on a hazardous chemical pipeline at a facility, an employee must verify zero-energy state by:
Answer: Testing the equipment to confirm that hazardous energy has been released or blocked
Verification of zero-energy state requires actually testing the equipment—not just observing valve position—to confirm isolation is effective.
A facility is required to submit a Tier II report under EPCRA Section 312. What is the annual reporting deadline for Tier II submissions?
Answer: March 1
Tier II emergency and hazardous chemical inventory reports are due to SERC, LEPC, and local fire departments by March 1 each year.
Which of the following best describes the purpose of a facility's written Chemical Hygiene Plan (CHP) required by OSHA 29 CFR 1910.1450?
Answer: To establish work practices, exposure controls, and procedures for protecting laboratory workers from hazardous chemicals