CHFM Emergency Management Preparedness 3 — Questions and Answers
Question 1: What is the primary function of the Emergency Operations Center (EOC) during a hospital mass casualty event?
- Coordinate resources, communications, and decision-making across the facility (Correct answer)
- Provide direct patient care to critically injured victims
- Manage media relations and public communications only
- Oversee supply chain procurement for routine operations
Correct answer: Coordinate resources, communications, and decision-making across the facility
The EOC serves as the centralized command hub that coordinates all operational, logistical, and informational activities during an emergency.
Question 2: Under CMS Conditions of Participation, how often must a hospital conduct a full-scale community-based emergency exercise?
- Every two years (Correct answer)
- Annually
- Every three years
- Once every five years
Correct answer: Every two years
CMS requires hospitals to conduct a full-scale community-based exercise at least every two years, alternating with an individual facility exercise.
Question 3: A facility manager discovers that a critical utility failure has rendered the nurse call system inoperable. Which continuity strategy should be implemented first?
- Activate a manual rounding protocol with increased staff presence (Correct answer)
- Request FEMA resources through the state emergency management agency
- Shut down the affected unit and transfer all patients
- Issue a media notice to redirect non-emergency patients
Correct answer: Activate a manual rounding protocol with increased staff presence
Manual rounding protocols are the immediate, practical continuity measure when electronic nurse call systems fail.
Question 4: Which term describes the predetermined chain of command that activates when a hospital's Incident Commander is unavailable?
- Succession planning (Correct answer)
- Unified command
- Area command
- Transfer of command
Correct answer: Succession planning
Succession planning within HICS designates pre-identified alternates for key command positions to ensure continuity of leadership.
Question 5: The PICS (Patient Information and Communication System) concept in emergency management is primarily designed to address which challenge?
- Reunifying patients with family members during and after a disaster (Correct answer)
- Allocating limited ventilators across multiple ICUs
- Tracking staff assignments during surge events
- Coordinating medication resupply with external pharmacies
Correct answer: Reunifying patients with family members during and after a disaster
PICS supports family reunification by providing a systematic way to share patient location information during mass casualty and disaster events.
Question 6: During a prolonged power outage, which clinical area requires the highest priority for emergency generator power in a hospital?
- Operating rooms and intensive care units (Correct answer)
- Administrative offices and billing departments
- Cafeteria and dietary services
- Gift shop and visitor waiting areas
Correct answer: Operating rooms and intensive care units
Life safety systems in ORs and ICUs—including ventilators, monitoring equipment, and surgical lighting—require immediate emergency power priority.
Question 7: What does the term 'just-in-time training' refer to in healthcare emergency preparedness?
- Training delivered immediately before or during an event for staff assigned new emergency roles (Correct answer)
- Annual credentialing training completed before the fiscal year ends
- Simulation drills conducted in the last quarter of the year
- Online modules assigned during new employee orientation
Correct answer: Training delivered immediately before or during an event for staff assigned new emergency roles
Just-in-time training provides rapid, focused instruction to staff at the moment they need it, often when assigned unfamiliar roles during an emergency.
What is the primary function of the Emergency Operations Center (EOC) during a hospital mass casualty event?