CHFM Compliance and Regulatory Standards 5 — Questions and Answers
Question 1: Under OSHA's Respiratory Protection Standard (29 CFR 1910.134), before an employee can wear a tight-fitting respirator, the employer must ensure which of the following?
- Annual fit test only
- Medical evaluation only
- Medical evaluation, fit test, and training (Correct answer)
- Training and fit test only
Correct answer: Medical evaluation, fit test, and training
OSHA requires medical evaluation, fit testing, and training before an employee uses a tight-fitting respirator.
Question 2: A hospital undergoes a triennial survey by The Joint Commission. During the survey, a Pattern of Failure (PoF) is cited. What does this designation mean?
- A single critical finding requiring immediate correction
- Multiple findings of the same standard across different areas (Correct answer)
- A finding that poses immediate threat to life
- A finding cited in two consecutive surveys
Correct answer: Multiple findings of the same standard across different areas
A Pattern of Failure (PoF) means the same or similar deficiency was found in multiple locations, units, or instances during the survey.
Question 3: The FGI Guidelines for Design and Construction of Hospitals are referenced by which regulatory authority to establish minimum space requirements?
- OSHA
- CMS
- State licensing agencies (Correct answer)
- EPA
Correct answer: State licensing agencies
Most state health facility licensing agencies adopt the FGI Guidelines as the minimum design and construction standard for healthcare facility planning.
Question 4: Under NFPA 25 (Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems), wet-pipe sprinkler systems must be hydrostatically tested at what pressure?
- 100 psi for 2 hours
- 150 psi for 2 hours
- 200 psi for 2 hours (Correct answer)
- 250 psi for 2 hours
Correct answer: 200 psi for 2 hours
NFPA 25 requires hydrostatic testing of existing wet-pipe sprinkler systems at 200 psi for 2 hours when the system is modified or shows signs of damage.
Question 5: A healthcare facility manager receives a Notice of Proposed Rulemaking (NPRM) from CMS. What is the appropriate initial action?
- Immediately implement the proposed changes
- Submit formal public comments during the comment period (Correct answer)
- Contact The Joint Commission for guidance
- File for a waiver from the proposed rule
Correct answer: Submit formal public comments during the comment period
An NPRM invites public comment before a rule is finalized; the facility should review and submit comments during the designated comment period.
Question 6: Under CMS requirements for Critical Access Hospitals (CAHs), what is the maximum number of inpatient beds allowed?
- 15
- 25 (Correct answer)
- 35
- 50
Correct answer: 25
CMS designates Critical Access Hospitals as rural hospitals with no more than 25 inpatient beds, with an average stay of 96 hours or less.
Question 7: Which accreditation organization uses the ISO 9001 quality management system integrated with its hospital accreditation standards?
- The Joint Commission
- HFAP
- DNV GL Healthcare (Correct answer)
- CIHQ
Correct answer: DNV GL Healthcare
DNV GL Healthcare integrates ISO 9001 quality management system requirements into its NIAHO hospital accreditation standards.
Under OSHA's Respiratory Protection Standard (29 CFR 1910.134), before an employee can wear a tight-fitting respirator, the employer must ensure which of the following?