A hospital project uses a unit-price contract for excavation. The actual quantity excavated is 40% greater than the estimated quantity. What contractual mechanism typically addresses this situation?
-
A
A termination for convenience clause
-
B
A quantity variation clause allowing renegotiation of unit prices beyond a threshold
-
C
A force majeure provision
-
D
A liquidated damages clause