CHA Preventive Maintenance Procedures 2 — Questions and Answers
Question 1: Which document is most critical for establishing a preventive maintenance (PM) schedule in a HACCP-regulated food facility?
- Equipment manufacturer's maintenance manual (Correct answer)
- Employee break schedule
- Pest control service log
- Customer complaint records
Correct answer: Equipment manufacturer's maintenance manual
The manufacturer's maintenance manual specifies recommended service intervals and procedures that form the foundation of a PM schedule.
Question 2: A food plant uses food-grade lubricants on equipment that contacts product. What is the PRIMARY reason for this requirement?
- They are cheaper than industrial lubricants
- Incidental contact with food will not create a safety hazard (Correct answer)
- They provide better corrosion resistance
- Regulatory agencies require lubrication logs
Correct answer: Incidental contact with food will not create a safety hazard
Food-grade lubricants (e.g., H1 classification) are formulated so that incidental food contact does not pose a health risk.
Question 3: After completing a maintenance task on a filler machine, which step is MOST important before resuming production?
- Update the PM log
- Perform a pre-operational sanitation inspection (Correct answer)
- Notify the shift supervisor by phone
- Order replacement parts for next service
Correct answer: Perform a pre-operational sanitation inspection
A pre-operational sanitation inspection ensures that tools, debris, and non-food-grade materials are removed before food production resumes.
Question 4: In HACCP terminology, a piece of equipment malfunction that could allow metal fragments into product would be classified as a:
- Prerequisite program failure
- Potential physical hazard at a CCP (Correct answer)
- Minor deviation
- Sanitation standard operating procedure (SSOP) gap
Correct answer: Potential physical hazard at a CCP
Metal fragments from faulty equipment constitute a physical hazard that must be controlled, often at a designated CCP such as a metal detector.
Question 5: A facility's PM program requires monthly belt inspection on a conveyor. An auditor finds the last inspection was performed 47 days ago. This is BEST described as:
- An acceptable variance within tolerance
- A deviation requiring corrective action documentation (Correct answer)
- A critical limit violation
- A calibration error
Correct answer: A deviation requiring corrective action documentation
Missing a scheduled PM interval is a deviation from the program that must be documented and corrected per the facility's procedures.
Question 6: Which element should be included in a PM work order to support HACCP traceability?
- Employee pay grade
- Date, equipment ID, parts used, and technician signature (Correct answer)
- Customer purchase order number
- Shift production yield
Correct answer: Date, equipment ID, parts used, and technician signature
Traceability in PM records requires identifying when work was done, on which equipment, what materials were used, and who performed the work.
Question 7: When scheduling preventive maintenance during production hours is unavoidable, what control is MOST important to implement?
- Post a sign warning employees
- Isolate or segregate the maintenance area to prevent product contamination (Correct answer)
- Reduce line speed by 10%
- Assign extra quality inspectors to downstream stations
Correct answer: Isolate or segregate the maintenance area to prevent product contamination
Physical isolation of the maintenance zone prevents tools, lubricants, and debris from contaminating product moving through adjacent areas.