CFS FEMA Regulations & NFIP Compliance 2 — Questions and Answers
Question 1: Under the NFIP, what is the minimum required freeboard above the Base Flood Elevation (BFE) for new residential construction in a Zone AE?
- 0 feet — structures need only meet BFE (Correct answer)
- 1 foot above BFE per FEMA minimum standard
- 2 feet above BFE as a federal mandate
- Freeboard is set solely by local ordinance, not FEMA
Correct answer: 0 feet — structures need only meet BFE
FEMA's minimum standard is that the lowest floor must be at or above BFE; any freeboard is a community or state add-on, not a federal NFIP requirement.
Question 2: A community receives a Letter of Final Determination (LFD) from FEMA. What does this signify?
- The community has been suspended from the NFIP
- A FIRM revision has been finalized and will become effective in 6 months (Correct answer)
- The community's CRS rating has been officially updated
- A Conditional Letter of Map Revision has been approved
Correct answer: A FIRM revision has been finalized and will become effective in 6 months
An LFD notifies the community that a revised FIRM has been finalized and will become effective 6 months after the LFD date.
Question 3: Which NFIP flood zone designation indicates a 0.2% annual chance flood area with no established BFE?
- Zone AO
- Zone AH
- Zone X (shaded) (Correct answer)
- Zone A99
Correct answer: Zone X (shaded)
Shaded Zone X (formerly Zone B) represents the 0.2% annual chance (500-year) flood area where BFEs are not determined.
Question 4: Under 44 CFR Part 60, what is the NFIP definition of 'substantial improvement' for an existing structure?
- Any improvement costing more than $10,000
- Any reconstruction or improvement whose cost equals or exceeds 25% of market value
- Any reconstruction or improvement whose cost equals or exceeds 50% of market value (Correct answer)
- Any improvement that increases the structure's footprint by more than 10%
Correct answer: Any reconstruction or improvement whose cost equals or exceeds 50% of market value
Substantial improvement means any reconstruction, rehabilitation, addition, or improvement of a structure whose cost equals or exceeds 50% of the market value of the structure.
Question 5: A Conditional Letter of Map Amendment (CLOMA) is issued by FEMA for what purpose?
- To temporarily suspend a community from the NFIP
- To indicate a structure or parcel would be excluded from the SFHA if a proposed project is built as shown (Correct answer)
- To officially remove a structure from the SFHA after construction
- To revise a FIRM based on new hydrologic data
Correct answer: To indicate a structure or parcel would be excluded from the SFHA if a proposed project is built as shown
A CLOMA is a pre-construction determination that a proposed lot or structure, if built as proposed, would be excluded from the SFHA.
Question 6: In Zone V coastal areas under the NFIP, what additional construction requirement applies that does not apply in Zone A?
- Structures must be elevated on fill only
- Structures must be elevated on open foundations (pilings/columns) free of obstruction below BFE (Correct answer)
- Structures require a variance from FEMA before any construction
- No basements are permitted, but enclosed foundations are allowed
Correct answer: Structures must be elevated on open foundations (pilings/columns) free of obstruction below BFE
Zone V requires structures to be elevated on pilings or columns with the area below BFE free of obstruction to allow wave action to pass beneath.
Question 7: Which document does a community's floodplain administrator use to grant or deny permits for development in the SFHA?
- Flood Insurance Rate Map (FIRM) alone
- Flood Insurance Study (FIS) alone
- Both the FIRM and accompanying FIS as a package (Correct answer)
- The National Flood Insurance Program Regulations (44 CFR)
Correct answer: Both the FIRM and accompanying FIS as a package
The FIRM and the FIS are companion documents; the FIS provides the technical data (BFEs, flood profiles) supporting the FIRM's flood zone delineations used in permitting.
Under the NFIP, what is the minimum required freeboard above the Base Flood Elevation (BFE) for new residential construction in a Zone AE?