FEMA Map Amendment & Revision Processes Flashcards
7 cards from real CFS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 FEMA Map Amendment & Revision Processes flashcards as text
What is the primary purpose of a Conditional Letter of Map Revision (CLOMR)?
Answer: To provide FEMA's official comment on whether a proposed project, if built as designed, would meet the requirements for a future LOMR
A CLOMR is FEMA's prospective review confirming that a proposed project meets NFIP criteria, giving developers regulatory certainty before committing resources to construction.
Why is obtaining a CLOMR particularly important for a real estate developer building in or near the SFHA?
Answer: It provides assurance before construction that the completed project will qualify for a LOMR, reducing financial risk
A CLOMR reduces financial risk by confirming upfront that the project's design satisfies FEMA standards, so developers know a LOMR is achievable before breaking ground.
After a construction project based on an approved CLOMR is completed, the next required step is to:
Answer: Submit a LOMR application with as-built certifications demonstrating the project was built per the approved design
A CLOMR does not itself change the FIRM; a follow-up LOMR with as-built certifications is required to officially revise the flood map after construction is complete.
Which scenario would most appropriately require a CLOMR-F?
Answer: A developer planning to place fill to remove a proposed subdivision from the SFHA before lots are sold or buildings are constructed
A CLOMR-F is the appropriate pre-construction step when a developer plans to place fill that will raise the site above the BFE, allowing FEMA to conditionally approve the plan before fill is placed.
FEMA's Flood Map Service Center (MSC) serves as the primary repository for:
Answer: Official FIRMs, Flood Insurance Studies, and associated amendment and revision documents including LOMAs and LOMRs
The FEMA MSC is the official source for current FIRMs, FIS reports, and all associated map change documents, making it the authoritative reference for surveyors researching a property's flood zone status.
When FEMA issues a LOMA or LOMR, how is the official flood map updated to reflect the change?
Answer: The FIRM panel is annotated with a letter suffix or notation referencing the amendment or revision, until the next Physical Map Revision incorporates the change
FEMA annotates the affected FIRM panel with a reference to the LOMA or LOMR, providing a documented link between the official map and the administrative action until a full Physical Map Revision can incorporate the change.
A surveyor determines that a property was successfully removed from the SFHA via a LOMA six years ago. A new FIRM has since been issued for the same community. What should the property owner be advised?
Answer: Check whether the new FIRM still shows the property outside the SFHA; if the new FIRM re-includes it, a new LOMA based on the new FIRM is required
LOMAs are tied to the FIRM in effect at the time of issuance; when a new FIRM is issued, an existing LOMA does not automatically carry forward, so property owners must verify their status on the new map.