A fence project is delayed because posts arrived three days late from the supplier. Which planning strategy would BEST reduce the impact of material delivery delays on the overall schedule?
-
A
Order materials well in advance and confirm delivery dates before scheduling installation
-
B
Add more crew members to the installation team
-
C
Reduce the number of project milestones
-
D
Schedule installation before permits are finalized