When scheduling a large commercial fence installation, what is the PRIMARY purpose of a critical path analysis?
-
A
To identify the sequence of tasks that determines the minimum project duration
-
B
To calculate the total labor cost for all tasks
-
C
To determine which subcontractors are available on specific dates
-
D
To list all required materials in order of installation