A customer calls mid-project to request an upgrade from chain-link to ornamental iron fencing. How should the CFP handle this change order?
-
A
Absorb the additional cost to maintain customer goodwill
-
B
Refuse all mid-project changes as a policy
-
C
Document the change in a written change order with revised pricing before proceeding
-
D
Make the change and bill the difference at the end