A fence contractor is hired to install security fencing at a facility handling hazardous waste. Which regulatory program governs physical security and fencing requirements at such sites?
Answer: EPA Resource Conservation and Recovery Act (RCRA)
EPA's RCRA regulations (40 CFR Part 264/265) require security measures including fences and gates at permitted hazardous waste treatment, storage, and disposal facilities.
What does the term 'competent person' mean in the context of OSHA excavation safety for fence post digging?
Answer: A person capable of identifying hazards and authorized to take corrective action
OSHA defines a competent person as someone capable of identifying existing and predictable hazards and authorized to take prompt corrective action to eliminate them.
Which safety sign color and format is used for ANSI Z535 'DANGER' signs at fence job sites to indicate an immediately hazardous situation?
Answer: Red header panel with white text
ANSI Z535.2 specifies that DANGER signs use a red header panel with 'DANGER' in white text, signifying an immediately life-threatening hazard.
Under IBC Section 1015, guards (guardrails) must be provided at open-sided elevated surfaces where the drop exceeds what height?
Answer: 30 inches
IBC Section 1015.2 requires guards at open-sided walking surfaces, mezzanines, and other areas that are located more than 30 inches above the floor or grade below.
A fence contractor's employee is injured on the job. Under OSHA 29 CFR 1904, within how many hours must the employer report an in-patient hospitalization to OSHA?
Answer: 24 hours
OSHA 1904.39 requires employers to report any work-related in-patient hospitalization to OSHA within 24 hours of learning of the incident.
Which document must a fence contractor review before installing a fence on a commercial property to identify underground utilities, drainage easements, and setback restrictions?
Answer: The site plan or grading plan approved by the local authority
The approved site plan or grading plan shows underground utilities, drainage swales, easements, and required setbacks that affect fence placement.
When installing a chain-link fence near an airport, which federal agency's regulations must the fence contractor coordinate with regarding height and location restrictions?
Answer: FAA (Federal Aviation Administration)