  1. A client requests that a fence project be completed two weeks earlier than originally scheduled. Which schedule compression technique involves adding resources to critical path tasks to shorten their duration?

    Answer: Crashing

    Crashing involves adding resources (such as extra crew or equipment) to critical path tasks to reduce their duration, usually at increased cost.

  2. Fast-tracking a fence project schedule means:

    Answer: Performing tasks in parallel that were originally planned sequentially

    Fast-tracking overlaps tasks that were planned to occur one after another, compressing the schedule at the cost of increased risk.

  3. Before scheduling installation of a fence along a property boundary, which document should the contractor review to confirm the exact boundary location?

    Answer: Survey plat or property survey

    A survey plat or property survey legally defines property boundaries and must be confirmed to avoid encroachment on neighboring land.

  4. In a fence project schedule, which task is the correct PREDECESSOR to 'install fence panels'?

    Answer: Set and cure posts

    Posts must be set and concrete cured before panels can be attached, making post installation the direct predecessor to panel installation.

  5. A contractor is scheduling a project where the excavation subcontractor is only available on Mondays and Tuesdays. This constraint is best categorized as a:

    Answer: Resource constraint

    A resource constraint limits when work can occur based on the availability of personnel, equipment, or subcontractors.

  6. Which scheduling practice helps ensure that a multi-crew fence project proceeds smoothly when one crew finishes a section ahead of schedule?

    Answer: Building lookahead schedules and maintaining a list of pull-forward tasks

    Lookahead schedules and pre-identified pull-forward tasks allow crews to immediately begin eligible work when they finish early, maintaining productivity.

  7. A project schedule baseline is BEST described as:

    Answer: The approved original schedule used to measure actual progress

    The schedule baseline is the approved, original project plan against which actual performance and deviations are measured throughout the project.