The 'loss ratio' adjustment in termination settlements under FAR 49.203 is applied when:
-
A
The contractor would have incurred a loss on the contract if fully performed
-
B
The government terminates more than 50% of the work
-
C
The contractor has multiple subcontracts
-
D
Progress payments exceed 80% of costs