A subcontractor on a fixed-price prime contract requests a price adjustment due to government-caused delays. Who has the legal standing to present this claim to the government?
-
A
The subcontractor directly, through a direct access clause
-
B
The prime contractor, who must sponsor the subcontractor's claim
-
C
Either party, at the election of the subcontractor
-
D
The subcontractor's surety company