Which standard practice should a CO follow when a contractor submits a Request for Equitable Adjustment (REA) for a government-caused delay?
-
A
Deny it immediately if the contract is FFP
-
B
Review the REA, conduct fact-finding, and negotiate a fair settlement before issuing a final decision
-
C
Issue a final decision within 10 days without negotiation
-
D
Forward the REA directly to the GAO for adjudication