CFCM Fundamentals & Core Concepts 3 — Questions and Answers
Question 1: Which FAR subpart establishes the policy that acquisition planning must begin as soon as a need is identified?
- FAR Subpart 7.1 (Correct answer)
- FAR Subpart 6.3
- FAR Subpart 15.2
- FAR Subpart 12.1
Correct answer: FAR Subpart 7.1
FAR Subpart 7.1 governs acquisition plans and requires planning to begin as early as possible in the acquisition cycle.
Question 2: What term describes the legal authority granted to a Contracting Officer to enter into, administer, or terminate contracts on behalf of the government?
- Delegation of Procurement Authority
- Warrant (Correct answer)
- Contracting Officer Representative designation
- Patent authority
Correct answer: Warrant
A warrant is the official document that grants a Contracting Officer the legal authority to bind the government in contractual agreements.
Question 3: Under the Competition in Contracting Act (CICA), what is the default competition requirement for federal acquisitions?
- Best value competition
- Full and open competition (Correct answer)
- Simplified acquisition procedures
- Set-aside for small businesses
Correct answer: Full and open competition
CICA mandates full and open competition as the default, allowing all responsible sources to compete for federal contracts.
Question 4: Which document serves as the primary vehicle for communicating the government's requirements to prospective offerors in a negotiated acquisition?
- Invitation for Bids (IFB)
- Request for Proposal (RFP) (Correct answer)
- Purchase Order
- Blanket Purchase Agreement
Correct answer: Request for Proposal (RFP)
A Request for Proposal (RFP) is used in negotiated acquisitions to solicit offers and allows for discussion and negotiation with offerors.
Question 5: What is the primary purpose of the Federal Acquisition Regulation (FAR)?
- To establish pay scales for federal procurement employees
- To codify uniform acquisition policies and procedures for executive agencies (Correct answer)
- To set maximum prices for commercial items
- To define security clearance requirements for contractors
Correct answer: To codify uniform acquisition policies and procedures for executive agencies
The FAR establishes uniform acquisition policies and procedures that all executive branch agencies must follow when procuring goods and services.
Question 6: A contractor who knowingly presents a false claim to the government may be liable under which federal statute?
- Anti-Kickback Act
- False Claims Act (Correct answer)
- Buy American Act
- Service Contract Labor Standards
Correct answer: False Claims Act
The False Claims Act imposes civil and criminal penalties on contractors who knowingly submit fraudulent claims or statements to the federal government.
Question 7: Which type of contract places the maximum cost risk on the contractor?
- Cost-Plus-Fixed-Fee (CPFF)
- Firm-Fixed-Price (FFP) (Correct answer)
- Cost-Plus-Incentive-Fee (CPIF)
- Time-and-Materials (T&M)
Correct answer: Firm-Fixed-Price (FFP)
Under a Firm-Fixed-Price contract, the contractor bears all cost risk because the price is set at award and does not change regardless of actual costs incurred.
Which FAR subpart establishes the policy that acquisition planning must begin as soon as a need is identified?