Under FAR 33.211, if a contracting officer issues a final decision on a claim over $100,000, the decision must be issued within how many days of receiving the claim?
-
A
30 days
-
B
60 days with notification of anticipated decision date required for complex claims
-
C
90 days
-
D
120 days