Under FAR 33.103, what must a contractor do before filing a formal claim to encourage resolution at the lowest possible level?
-
A
File a protest with the GAO
-
B
Attempt to resolve the issue through good-faith discussions with the CO
-
C
Obtain legal counsel and submit a demand letter
-
D
Request an independent government cost estimate