CFCM Contract Planning & Formation 5 โ Questions and Answers
Question 1: Which FAR part governs the use of Multiple Award Schedule (MAS) contracts administered by GSA?
- FAR Part 8 (Correct answer)
- FAR Part 12
- FAR Part 13
- FAR Part 16
Correct answer: FAR Part 8
FAR Part 8 (Required Sources of Supplies and Services) governs ordering from GSA Federal Supply Schedules and Multiple Award Schedule contracts.
Question 2: A Synopsis waiver is permitted under FAR 5.202 when the contracting officer determines that:
- The acquisition exceeds $150,000
- Advance notice would compromise national security (Correct answer)
- The requirement is below the micro-purchase threshold only
- The contractor has already been identified
Correct answer: Advance notice would compromise national security
FAR 5.202(a)(1) permits waiving the synopsis requirement when the contracting officer determines that publicizing would compromise national security.
Question 3: When evaluating past performance in a source selection, a contractor with no relevant past performance record should typically be rated as:
- Unacceptable, due to lack of demonstrated capability
- Unknown risk, neither favored nor unfavored (Correct answer)
- Neutral, treated the same as a marginal rating
- Acceptable, assuming the contractor can perform
Correct answer: Unknown risk, neither favored nor unfavored
FAR 15.305(a)(2)(iv) states that offerors with no relevant past performance record shall be evaluated as an unknown risk, neither favorably nor unfavorably.
Question 4: The Procurement Integrity Act (PIA) prohibits a former agency official who served as a 'procurement official' from receiving compensation from a contractor for one year if:
- The official worked on any federal contract during their career
- The official participated personally and substantially in a contract over $10 million (Correct answer)
- The contractor submitted any proposal while the official was employed
- The official had any supervisory role over contracting personnel
Correct answer: The official participated personally and substantially in a contract over $10 million
41 U.S.C. ยง2104 (PIA) bars a procurement official who personally and substantially participated in a contract or subcontract exceeding $10 million from receiving compensation from that contractor for one year after leaving government.
Question 5: Under FAR 16.505, when placing task orders under a multiple award IDIQ contract, the ordering contracting officer must provide each awardee a:
- Full and open competition opportunity regardless of order value
- Fair opportunity to be considered for each order above $3,500 (Correct answer)
- Right to protest order awards to the GAO regardless of value
- Minimum guaranteed task order value equal to their share of the contract
Correct answer: Fair opportunity to be considered for each order above $3,500
FAR 16.505(b)(1) requires that each awardee on a multiple award contract receive a fair opportunity to be considered for task or delivery orders exceeding $3,500.
Question 6: A Performance Work Statement (PWS) differs from a Statement of Work (SOW) primarily because a PWS:
- Specifies how the contractor must perform each task in detail
- Describes outcomes and performance standards rather than methods (Correct answer)
- Is only used for commercial item acquisitions under FAR Part 12
- Requires mandatory use of government-furnished equipment
Correct answer: Describes outcomes and performance standards rather than methods
A PWS focuses on measurable outcomes, performance standards, and quality levels, allowing contractors flexibility in how they accomplish the work, unlike a SOW which specifies methods.
Question 7: Which of the following is a characteristic unique to Cost-Plus-Award-Fee (CPAF) contracts compared to other cost-reimbursement types?
- The fee amount is fixed at contract award and cannot change
- The award fee determination by the government is not subject to the Disputes clause (Correct answer)
- The contractor bears cost risk above the estimated cost
- Award fee ratings must be reviewed by GAO upon contractor request
Correct answer: The award fee determination by the government is not subject to the Disputes clause
FAR 16.405-2 states that award fee determinations are made unilaterally by the government and are not subject to the Disputes clause, making them final and not appealable.
Which FAR part governs the use of Multiple Award Schedule (MAS) contracts administered by GSA?