Under FAR 32.202-1, performance-based payments must be structured so that the total amount of these payments at any time does NOT exceed:
-
A
The total costs incurred to date
-
B
The value of the contract work completed
-
C
90% of the contract price
-
D
The amount authorized by the Head of Contracting Activity