Under FAR 52.249-8, what is the contractor's obligation when the government issues a cure notice for a default?
-
A
File a protest with the GAO within 10 days
-
B
Cure the failure within 10 days or show cause why the contract should not be terminated
-
C
Request an equitable adjustment within 30 days
-
D
Suspend performance until the dispute is resolved