A field builder discovers that underground utilities were not properly marked before excavation begins. What is the FIRST action to take?
-
A
Continue excavation carefully using hand tools
-
B
Stop work immediately and call 811 to have utilities located
-
C
Proceed with a spotter watching for utility lines
-
D
Notify the owner and continue on schedule