CFB Cost Estimation 2 — Questions and Answers
Question 1: Which estimating method uses historical cost data from similar completed projects to project costs for a new project?
- Analogous estimating (Correct answer)
- Parametric estimating
- Bottom-up estimating
- Three-point estimating
Correct answer: Analogous estimating
Analogous estimating relies on actual costs from comparable past projects as a basis for estimating the current project.
Question 2: A field builder estimates lumber costs at $8,000 with a 10% contingency. What is the total budgeted lumber cost?
- $8,800 (Correct answer)
- $8,080
- $8,100
- $8,400
Correct answer: $8,800
$8,000 × 1.10 = $8,800, which includes the 10% contingency added to the base estimate.
Question 3: What does the term 'allowance' represent in a construction cost estimate?
- A reserved sum for undefined or uncertain scope items (Correct answer)
- The contractor's profit margin
- The cost of permits and inspections
- A discount offered to the owner
Correct answer: A reserved sum for undefined or uncertain scope items
An allowance is a placeholder dollar amount included for scope items whose details are not yet fully defined at the time of estimating.
Question 4: Which of the following best describes a 'unit price' contract?
- Payment is based on measured quantities of work at agreed prices per unit (Correct answer)
- A fixed total price regardless of actual quantities
- Cost of work plus a fixed fee
- Payment based on time and materials used
Correct answer: Payment is based on measured quantities of work at agreed prices per unit
In a unit price contract, the owner pays for actual measured quantities multiplied by the agreed unit price for each work item.
Question 5: When estimating concrete formwork, which factor most directly affects the cost per square foot?
- Complexity of form shape and reuse factor (Correct answer)
- Concrete compressive strength
- Type of reinforcing steel
- Curing method selected
Correct answer: Complexity of form shape and reuse factor
Complex form shapes require more labor and custom material, while the reuse factor determines how many times forms can be used, reducing per-use cost.
Question 6: A project has a Cost Performance Index (CPI) of 0.85. What does this indicate?
- The project is over budget — spending $1.18 for every $1.00 of work completed (Correct answer)
- The project is under budget — spending $0.85 for every $1.00 of work completed
- The project is 15% ahead of schedule
- The project is 15% behind schedule
Correct answer: The project is over budget — spending $1.18 for every $1.00 of work completed
A CPI below 1.0 means costs exceed the budgeted value of work done; at 0.85 you are spending about $1.18 per dollar of earned value.
Question 7: Which document typically serves as the primary basis for a detailed quantity takeoff in field construction?
- Construction drawings and specifications (Correct answer)
- Bid tabulation sheet
- Subcontractor proposals
- Owner's project budget
Correct answer: Construction drawings and specifications
Detailed quantity takeoffs are derived directly from the construction drawings and specifications, which define exact dimensions, materials, and quality standards.
Which estimating method uses historical cost data from similar completed projects to project costs for a new project?