Under the percentage-of-completion method for long-term contracts, revenue is recognized:
-
A
Only when the project is fully completed
-
B
Based on the proportion of costs incurred to total estimated costs
-
C
When cash payments are received from the client
-
D
Equally over the duration of the contract