Value at Risk (VaR) at a 95% confidence level and a 1-day horizon means:
-
A
The portfolio will lose more than the VaR amount 5 days out of every 100
-
B
The portfolio will never lose more than the VaR amount
-
C
The expected loss over one day is exactly equal to VaR
-
D
VaR equals 95% of the maximum possible daily loss