Which of the following best describes 'final stabilization' as defined under the EPA Construction General Permit?
-
A
All grading and earthwork has been completed
-
B
All soil-disturbing activities are complete and a uniform perennial vegetative cover of at least 70% density is established, or equivalent non-vegetative cover
-
C
The site has received a certificate of occupancy
-
D
All sediment basins have been removed from the site