What is the correct procedure when an inspector discovers a previously unidentified discharge point that is not addressed in the SWPPP?
-
A
Ignore it if no active discharge is occurring at the time of inspection
-
B
Document the new discharge point and require the SWPPP to be updated to address it
-
C
Install a BMP at the location without updating the SWPPP
-
D
Notify only the state agency and take no site-level action