Which of the following is a PRIMARY design consideration when sizing a sediment basin outlet structure?
-
A
The basin must drain completely within 24 hours of storm cessation
-
B
The outlet must handle the 10-year peak flow without overtopping the embankment
-
C
The outlet pipe diameter must match the inlet ditch width
-
D
The outlet must be constructed of HDPE to prevent corrosion