Which of the following best describes the 'corrective action deadline' concept in storm water inspection communication?
-
A
The date by which the inspector must submit the report
-
B
A specific date by which identified deficiencies must be repaired and verified, typically specified in the corrective action notice
-
C
The expiration date of the SWPPP permit
-
D
The deadline for the contractor to respond to emails