During a routine inspection, an inspector discovers that a subcontractor is operating without being listed on the site's SWPPP. What is the appropriate corrective action?
-
A
Issue a stop-work order to the subcontractor immediately
-
B
Add the subcontractor to the SWPPP and ensure they receive a copy of relevant sections
-
C
Report the subcontractor to the state environmental agency
-
D
Require the subcontractor to obtain a separate NPDES permit