CESSWI Regulatory Compliance & Reporting 2 — Questions and Answers
Question 1: Under the NPDES Construction General Permit, what is the maximum allowable turbidity benchmark for discharges to waters supporting cold-water fisheries?
- 10 NTU above background
- 25 NTU above background (Correct answer)
- 50 NTU above background
- 100 NTU above background
Correct answer: 25 NTU above background
The EPA's CGP sets a turbidity benchmark of 25 NTU above background for discharges to cold-water fisheries, which are more sensitive aquatic ecosystems.
Question 2: Which federal law primarily governs the regulation of stormwater discharges from construction sites as a point source of pollution?
- Safe Drinking Water Act
- Resource Conservation and Recovery Act
- Clean Water Act (Correct answer)
- National Environmental Policy Act
Correct answer: Clean Water Act
The Clean Water Act Section 402 establishes the NPDES permit program, which regulates stormwater discharges from construction sites as point sources.
Question 3: A construction project disturbs 0.8 acres. Under federal NPDES rules, is a permit required?
- Yes, all earth disturbance requires a permit
- No, only sites disturbing 1 acre or more require a permit (Correct answer)
- Yes, but only if within 100 feet of a waterbody
- No, permits are only required for sites over 5 acres
Correct answer: No, only sites disturbing 1 acre or more require a permit
Federal NPDES Construction General Permits apply to sites disturbing 1 acre or more of land, so a 0.8-acre project does not trigger the federal permit threshold.
Question 4: What document must an operator submit to notify the permitting authority before construction begins under most NPDES Construction General Permits?
- Notice of Termination (NOT)
- Discharge Monitoring Report (DMR)
- Notice of Intent (NOI) (Correct answer)
- Erosion Control Plan (ECP)
Correct answer: Notice of Intent (NOI)
A Notice of Intent (NOI) is submitted to obtain coverage under the NPDES Construction General Permit before earth-disturbing activities begin.
Question 5: Which scenario would trigger the need to file a Notice of Termination (NOT) under the NPDES CGP?
- When a new contractor takes over site operations
- When the SWPPP is updated significantly
- When final stabilization has been achieved and permit coverage is no longer needed (Correct answer)
- When a rainfall event exceeds 1 inch in 24 hours
Correct answer: When final stabilization has been achieved and permit coverage is no longer needed
A Notice of Termination is filed once final stabilization has been achieved and the operator no longer needs permit coverage for the site.
Question 6: Under the 2017 EPA Construction General Permit, how soon after a qualifying storm event must a post-storm inspection be conducted?
- Within 24 hours
- Within 72 hours (Correct answer)
- Within 7 days
- Within 14 days
Correct answer: Within 72 hours
The 2017 EPA CGP requires post-storm inspections to be conducted within 72 hours after a storm event of 0.25 inches or more.
Question 7: Which of the following best describes a 'qualified inspector' under most state NPDES construction stormwater programs?
- Any licensed professional engineer
- A person trained to evaluate BMPs and identify compliance issues (Correct answer)
- An EPA regional staff member
- Any employee of the general contractor
Correct answer: A person trained to evaluate BMPs and identify compliance issues
A qualified inspector is someone trained to recognize and evaluate the effectiveness of BMPs and identify compliance deficiencies, though specific credentials vary by state.
Under the NPDES Construction General Permit, what is the maximum allowable turbidity benchmark for discharges to waters supporting cold-water fisheries?