A construction site's SWPPP identifies a sediment basin as a required BMP. An inspector finds the basin not yet installed despite grading having begun. What documentation action is required?
-
A
Note the absence as an 'observation' without further action
-
B
Record the deficiency, issue a corrective action notice specifying the required installation deadline, and follow up in the next inspection
-
C
Halt the inspection and leave the site
-
D
Approve a verbal commitment from the contractor as sufficient documentation