← All CESSWI Flashcard Decks

Erosion Control BMPs Flashcards

7 cards from real CESSWI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Erosion Control BMPs flashcards as text
  1. An inspector observes that fiber rolls installed on a slope have gaps larger than 1 inch between the roll and the soil surface. What problem does this create?

    Answer: Runoff bypasses the roll by flowing underneath rather than being slowed

    Gaps beneath fiber rolls allow runoff to channel under the device, bypassing its flow-retarding function entirely.

  2. Which of the following is a key advantage of biodegradable erosion control blankets over plastic netting blankets?

    Answer: They do not need to be removed and will not entangle wildlife

    Biodegradable blankets decompose naturally, eliminating wildlife entanglement hazards and the labor cost of removal after vegetation establishes.

  3. A temporary seeding BMP specifies using annual ryegrass. What is the PRIMARY purpose of annual ryegrass in this application?

    Answer: Rapid germination and cover to protect soil until permanent species establish

    Annual ryegrass germinates quickly, providing fast interim ground cover to protect disturbed soil until slower-establishing permanent species take hold.

  4. What is the recommended maximum ponding depth behind a rock check dam in a drainage swale?

    Answer: 1.5 feet

    Rock check dams are typically designed to limit ponding to approximately 1.5 feet to prevent overtopping damage and upstream saturation.

  5. During a post-storm inspection, an inspector finds that a silt fence has been undermined by concentrated flow. What does this indicate about the original BMP design?

    Answer: The silt fence was placed in a concentrated flow path where it should not have been used

    Silt fences are designed for sheet flow only; placement in concentrated flow areas is a fundamental design error that leads to failure.

  6. Which erosion control BMP is MOST appropriate for protecting a freshly graded cut slope in a semi-arid climate where irrigation is not available?

    Answer: Bonded fiber matrix (BFM) hydraulic mulch

    BFMs create a continuous bonded matrix that protects soil and retains moisture to support seed germination even in dry conditions without irrigation.

  7. According to SWPPP requirements, how soon after rain events must a CESSWI-level inspection of erosion controls be conducted?

    Answer: Within 24 hours after a 0.25-inch or greater rain event

    Most Construction General Permits require inspection within 24 hours following a qualifying storm event (typically ≥0.25 inch) to assess BMP performance.