A facility stores large quantities of chlorine gas. Which federal regulatory program requires the facility to conduct an Offsite Consequence Analysis (OCA)?
-
A
RCRA Subtitle C hazardous waste management program
-
B
EPA's Risk Management Program (RMP) under Clean Air Act Section 112(r)
-
C
OSHA's Process Safety Management (PSM) standard
-
D
CERCLA Emergency Notification requirements