A manufacturer's ERP plans production without considering actual machine capacity, causing frequent schedule overloads. Which system is best suited to generate finite-capacity, constraint-based schedules?
-
A
Advanced planning and scheduling (APS) system
-
B
Customer relationship management (CRM) system
-
C
Electronic data interchange (EDI) translator
-
D
Transportation management system (TMS)