A Product Owner wants to maximize value delivered in the next Sprint. The team has capacity for 40 story points. Option A delivers 30 points of business value using 40 story points. Option B delivers 28 points of business value using 25 story points, leaving room for Option C which delivers 8 points of value. Which selection best reflects value-driven development?
-
A
Choose Option A alone because it uses full team capacity
-
B
Choose Options B and C together for a combined 36 points of value using 33 story points
-
C
Choose Option A because it has the highest individual value score
-
D
Ask the team to split Option A into smaller stories to fit more work