Which characteristic best describes a well-managed Product Backlog according to Scrum principles?
-
A
It is locked at the start of each Sprint and cannot be changed until the Sprint Review
-
B
It is detailed, estimated, emergent, and prioritized (DEEP)
-
C
It contains only items that have been approved by the Scrum Master
-
D
It is maintained jointly by the Product Owner and the project manager